Chapman Freeborn Moves 102t Rotor by Antonov An-124
Chapman Freeborn has completed an Antonov An-124 charter from Germany to Malaysia carrying a 102.8-tonne power plant generator rotor and transport frame. The shipment departed Stuttgart in July 2026 following specialist repair work in Europe. The rotor had also undergone…

Chapman Freeborn has completed an Antonov An-124 charter from Germany to Malaysia carrying a 102.8-tonne power plant generator rotor and transport frame.
The shipment departed Stuttgart in July 2026 following specialist repair work in Europe. The rotor had also undergone high-speed balancing in the UK before being prepared for its return to a Malaysian power plant.
With a total cargo weight of 102,847 kg, the operation required an An-124 and careful planning around payload, fuel, routing and airport infrastructure.

At Stuttgart Airport, specialist lifting equipment was used to transfer the rotor and its transport frame from a heavy-duty road transporter into the aircraft, with particular attention paid to load positioning and weight distribution.
Because of the shipment’s weight, the aircraft could carry only limited fuel, requiring five intermediate stops before reaching Malaysia.
High summer temperatures created further performance constraints, while routing options were reduced by restrictions linked to the conflict in the Middle East.
“With a shipment of this scale, the challenge is not just finding an aircraft capable of carrying the cargo, but managing the operational constraints that come with it,” said Anton Lomakin, VP Cargo Airchartering – ASEAN at Chapman Freeborn.
The charter also required close coordination between Chapman Freeborn teams in Germany and Singapore, covering cargo inspections, customs procedures, specialist ground handling, airport slots and oversized road transport restrictions.
“With so many parties involved, there were several critical decisions to be made at different stages of the shipment,” said Max Pätzel, Cargo Charter Broker at Chapman Freeborn Germany.
Air transport was selected to reduce overall transit time, with sea freight expected to take around two months each way.
The generator rotor was delivered to Malaysia for return to service at the power plant.