Advertise

      The world leading magazine of heavy lifting and transport equipment for construction, energy, maritime and industry

Rate this post

Sarens has been involved in the load-in, load-out, transport, and storage of several monopiles and transition pieces for the St. Nazaire Offshore Wind Farm since January 2021. The work is being performed at the port of La Rochelle in France.

As part of its agreement with DEME Offshore, Sarens will offload and transport monopiles and transition pieces weighing a maximum of 980T and measuring 62 metres long. During load in, Sarens will transport four monopiles and transition pieces in two days. During load out, they will transport and load in three monopiles and three transition pieces in two days. A total of two operators and dockers will be involved in the operation.

The vessel cranes will be unloading the transition pieces on temporary supports at the quayside before being taken by the Sarens TP Handler. The use of the TP Handler is a new concept with several advantages, including increased safety because all preparation is done at ground level. It was certified with a load test in Wolvertem and sent by road from Belgium to France, with delivery just in time to limit its presence on site. The TP handler was then assembled within one week. 

The vessel cranes will also be unloading some monopiles directly onto SPMTs equipped with saddles, while others will be placed in quayside storage areas organised by Sarens. To that end, Sarens and a local subcontractor have constructed 16-18 dunes, ranging in height from 2,1-2,6 metres, for monopile storage. Sarens has also organised the on-site steel support for 48 transition pieces. 20 load-ins were done during 2021 and 20 out of the 29 load-outs are already completed. 

Share This Post:

related news about Heavy transport