HS2 Deploys 125t Gantry Crane for Curzon Viaduct Decks
HS2 has installed a 125-tonne gantry crane on the Curzon approaches in Birmingham, where it will support the installation of more than 1,500 reinforced concrete deck slabs. The crane will operate across the interconnected viaduct structures leading into the future…

HS2 has installed a 125-tonne gantry crane on the Curzon approaches in Birmingham, where it will support the installation of more than 1,500 reinforced concrete deck slabs.
The crane will operate across the interconnected viaduct structures leading into the future Birmingham Curzon Street station and is expected to remain in use for around 18 months.
A total of 1,516 precast deck slabs will be positioned as construction progresses along the approaches.
The gantry crane has been designed to move along the viaduct alignment, allowing slabs to be lifted and placed directly into position while reducing reliance on large mobile cranes working from ground level.
Installation work is also taking place above Lawley Middleway, requiring a programme of overnight road closures as deck sections are positioned across the route.
The Curzon approaches form a key part of the infrastructure connecting HS2 into Birmingham city centre, with the viaduct system carrying trains towards the new station.
The latest phase marks a significant step in the construction of the elevated structures, with lifting and deck installation activity set to continue throughout the coming months.