Mammoet Installs 3,700t Hamburg Bridge in Under 24 Hours

Mammoet has completed the transport and installation of Hamburg’s new 3,700-tonne Sternbrücke railway bridge in less than 24 hours, using 272 axle lines of self-propelled modular transporters. The bridge was fully assembled beside Max-Brauer-Allee before being moved approximately 500 metres…

Lena Johnson1 min read
Mammoet Installs 3,700t Hamburg Bridge in Under 24 Hours
Rate this post

Mammoet has completed the transport and installation of Hamburg’s new 3,700-tonne Sternbrücke railway bridge in less than 24 hours, using 272 axle lines of self-propelled modular transporters.

The bridge was fully assembled beside Max-Brauer-Allee before being moved approximately 500 metres through the city to its final position.

Mammoet used two SPMT configurations, each comprising four trains, together with 16 climbing jacks rated at 500 tonnes each.

Space constraints were a major challenge. At the narrowest point of the route, clearance between the bridge and surrounding buildings was only around 30 cm.

d2cfebc3 24c7 ee29 c02f 379e30005d4b

The bridge was initially jacked from a height of two metres to 4.5 metres to allow the SPMTs to move beneath it. Once the full load had been transferred to the transporters, the structure was driven sideways onto Max-Brauer-Allee.

A second jacking operation raised the bridge by a further 1.5 metres to clear the new abutments.

After travelling around 500 metres, the bridge was rotated by 45 degrees using the SPMTs before being lowered 1.8 metres into its final position.

Mammoet had previously carried out 3D scans of the site and transport route, with the data incorporated into its Move3D engineering platform to plan the movement through the confined urban environment.

The Sternbrücke carries around 1,000 long-distance, regional and commuter trains each day, while the roads beneath handle tens of thousands of vehicles.

Pre-assembling the bridge allowed the replacement to be completed with significantly less disruption than conventional on-site construction. The new Sternbrücke reopened on 31 August 2026 after a six-week closure.

Rate this article
Rate this post
Found it useful? Share it with your network
Get stories like this every weekdayFree newsletter, read by 120,000 industry professionals.
Subscribe free

AdvertisementAdvertise here

Regal RexnordTII SCHEUERLE

Read more in MOVE IT Magazine

Features, interviews and reports on the biggest lifts and moves. Free for registered readers.