Sarens Moves 4,000t Bridge on 126 SPMT Axle Lines
Sarens has installed a 4,000-tonne bowstring bridge over the E40 motorway in Bertem, Belgium, on behalf of Victor Buyck Steel Construction. The new steel structure measures 130 metres long, 27 metres wide and 30 metres high. It replaces the former…

Sarens has installed a 4,000-tonne bowstring bridge over the E40 motorway in Bertem, Belgium, on behalf of Victor Buyck Steel Construction.
The new steel structure measures 130 metres long, 27 metres wide and 30 metres high. It replaces the former Tervuursesteenweg crossing, which had deteriorated and could no longer be renovated.
Sarens carried out the works in two phases between July and October 2026. During the first phase, from 14 to 24 July, the company used four CS1000 jacking towers to raise the bridge, which weighed around 1,800 tonnes at that stage, to transport height.
In the second phase, after the concrete deck had been added, the bridge was moved around 230 metres from its assembly area beside the motorway to its final position. For the transport, Sarens deployed 126 axle lines of K24-ST self-propelled modular transporters, supported by six power pack units.
The installation was completed during a full overnight closure of the E40, requiring detailed planning and precise execution. One of the main challenges was the road’s inclination in two directions, which required analysis of the transport route in AutoCAD.
To reduce the risk of torsion during the move, an inclinometer monitoring system was installed at both ends of the bridge, allowing the SPMT operator to continuously monitor levels and make adjustments during transport.
According to Sarens, the wider project forms part of the renewal of the Tervuursesteenweg crossing commissioned by the Flemish Roads and Traffic Agency. The new 130-metre span will cross the motorway without intermediate supports in the central reservation, improving safety and helping to limit disruption to traffic.