PTSC and Semco Win 6,800t Fengmiao 2 Substation Contract
PTSC M&C and Semco Maritime have signed an EPC contract for the Fengmiao 2 offshore substation, covering a topside, jacket and suction bucket foundations with a combined structural weight of approximately 6,800 tonnes. Under the contract, the consortium will handle…

PTSC M&C and Semco Maritime have signed an EPC contract for the Fengmiao 2 offshore substation, covering a topside, jacket and suction bucket foundations with a combined structural weight of approximately 6,800 tonnes.
Under the contract, the consortium will handle engineering, procurement, fabrication, load-out, offshore hook-up, testing and commissioning of the offshore substation.
PTSC M&C will carry out detailed design of the jacket and suction bucket foundations and fabricate all major structures, including the topside, jacket and foundations. Its scope also includes structural steel procurement, load-out and selected offshore hook-up and structural completion work.
Semco Maritime will lead topside engineering, procurement of electrical equipment and systems, together with offshore testing and commissioning.
Fabrication is scheduled to begin in 2028.
Offshore transportation and installation will follow in the second half of 2029, together with hook-up, testing and commissioning. Offshore completion is targeted for November 2029.
The new contract follows the consortium’s work on Fengmiao 1, where the offshore substation reached energisation in October 2026, two months ahead of schedule following a three-month offshore campaign.
Fengmiao 1 also recorded more than 2.6 million working hours without a lost-time injury.
The Fengmiao 2 award continues the partnership between PTSC M&C, Semco Maritime, Copenhagen Infrastructure Partners and Copenhagen Offshore Partners as offshore wind development expands across Taiwan and the wider Asia-Pacific region.