Hareket Completes Heavy Lifting for Ramhan Island Bridge in Abu Dhabi

Hareket
Rate this post

Hareket has successfully completed the heavy lifting operations for the Ramhan Island Bridge project in Abu Dhabi, United Arab Emirates, marking a major milestone in the infrastructure development. The company lifted 24 bridge girders, each weighing 95 tons, as part of this critical phase.

D8

For this operation, Hareket deployed a 2,200-ton capacity crawler crane, a solution chosen over traditional barge cranes. This innovative approach proved to be both more efficient and cost-effective, eliminating the need for marine equipment and significantly reducing logistical complexity.

Hareket

The use of the crawler crane allowed Hareket to meet all technical and safety requirements while also achieving a reduction in the overall project cost.