The world leading magazine of heavy lifting and transport equipment for construction, energy, maritime and industry

Wupper Bridge Replacement with Liebherr Cranes

Wupper Bridge
Rate this post

The damaged Hammesberg Wupper Bridge, constructed in 1965, is undergoing replacement due to severe damage. The bridge, closed to vehicles over 30 tonnes, faced a speed limit of 30 km/h. To minimize closure time, a prefabricated parts construction method was chosen.

Two Liebherr mobile cranes, an LTM 1650-8.1 from Autokrane Schares GmbH and an LTM 1450-8.1 from Dornseiff Autokrane & Schwertransporte GmbH, performed tandem lifts to place eight 85-tonne precast concrete elements onto the abutments over the Wupper.

Wupper Bridge

The unique tandem lift involved the LTM 1650-8.1 lifting parts from one side of the river, reaching its lifting capacity limit. The LTM 1450-8.1, positioned on the other side, took over, with technicians in a safety cage attaching the hook to a special triangular crossbeam. Schares project manager Eric Reichmann highlighted the necessity of this approach, stating that even an 800-tonne crane wouldn’t have sufficed due to space constraints.

Wupper Bridge

The tandem lift, utilizing a 160-tonne triangular crossbeam and an additional mobile crane, successfully installed eight 32-meter-long reinforced concrete girders across the Wupper in two days. The bridge is expected to reopen to traffic in the spring.

Wupper Bridge

Share This Post: