First 1,350t Nordseecluster B Monopiles Arrive at Eemshaven
The first monopile foundations for the Nordseecluster B offshore wind project have arrived at Buss Terminal Eemshaven in the Netherlands, marking the next stage in the development of the German North Sea scheme. RWE said the first 10 foundations have…

The first monopile foundations for the Nordseecluster B offshore wind project have arrived at Buss Terminal Eemshaven in the Netherlands, marking the next stage in the development of the German North Sea scheme.
RWE said the first 10 foundations have now been successfully unloaded at the heavy-lift terminal. The monopiles are around 81 metres long on average and weigh approximately 1,350 tonnes each.

A total of 60 monopile foundations for Nordseecluster B will be handled at Eemshaven this year and next. The units are being manufactured and supplied by Dajin Heavy Industry.
Nordseecluster is being developed in two phases around 50 km north of the island of Juist. The first phase, Nordseecluster A, has a capacity of 660 MW and is due to be fully operational in early 2027.

The second phase, Nordseecluster B, will add a further 900 MW. Installation of the foundations is scheduled to begin next year, with turbine installation following in 2028. Commercial operation is planned for early 2029.
Once completed, the full Nordseecluster project will have a total capacity of around 1.6 GW and is expected to generate approximately 6.5 TWh of electricity annually.
RWE said the use of Buss Terminal Eemshaven provides the large storage areas and port infrastructure required for handling the monopiles and preparing them for offshore installation.