Advertisement

      The world leading magazine of heavy lifting and transport equipment for construction, energy, maritime and industry

Allelys delivers eight transformes to Shetland Islands

Rate this post

Allelys has recently completed the delivery and installation of eight transformers for two separate projects, the Kergord Energy Station and Viking Energy Substation, on the Shetland Islands. The first project involved transporting four transformers, all weighing 168te and measuring 7.5m long, 4m wide and 4.5m high, using a 15 axle modular trailer from Lerwick Port to the Kergord Substation. 

2S5A3315 0972 copy

The units arrived in pairs into the port and were offloaded by a geared vessel. As one was temporarily stored, another was transported to the site. The cargo, which measured 35m long, 4m wide and 5.5m high, had to traverse multiple steep hills into the site, requiring two tractor units to pull the units up the first hill. They were then transhipped to an 18 axle SPMT, manoeuvred up the second hill and down the final steep hill into site. The transport route was then repeated for the unit left in storage, before the second pair arrived into the port and the whole operation repeated. 

2S5A3673 1169 copy

Once on site, they were installed using jacking and skidding techniques in multiple stages. Firstly, transformers one and two were stooled in front of plinth and rotated 90 degrees, they were then jacked and skidded into position. The operation was then replicated for transformers three and four.  

For the second project, the four transformers, all weighing 94te, arrived via barge into Rotterdam, where they were transhipped via mobile crane onto Allelys 2 bed 4 trailers and ferried over in pairs to Immingham. 

DJI 0152 0138 copy

The Allelys team were tasked with the 400 mile road transportation to Aberdeen, arranging the sea transportation to Lerwick Port, and onwards road transportation to Viking Energy Substation with a total transport length of 28m and height of 4.8m. Once on site, the transformers were then offloaded externally to be assembled and built, before being jacked and skidded onto the plinth.

“With multiple units arriving from different countries in such a remote part of the UK, this was not an easy task. These multi-phase and multi-modal projects really showcased our range of equipment and techniques, incorporating the team’s dedicated project management and engineering services over several months,” said Zac Smout, Senior Project Manager at Allelys. 

Share This Post: