Partnership

      The world leading magazine of heavy lifting and transport equipment for construction, energy, maritime and industry

Rate this post

The Collett Team were contracted to provide a door-to-door service, including the project management, engineering and the transport of two 160Te shunt reactors. The shunt reactors were transported in three stages before arriving at the substation site. First, the Collett Team worked in partnership with a trusted European partner to transport the shunt reactors ahead of their arrival in the UK. Our Projects Department were then responsible for all port operations including the loading of the vessel, also chartered by Collett, for the 4800 miles to the Port of Leith in Scotland.

Neart na Gaoithe Girder Bridge

Working closely with the port, the teams carefully planned the cargo’s discharge, including providing crane lifting plans and an agreed programme of works for all loading and discharge operations. Once at the port, utilising an 800Te crane, the shunt reactors were discharged onto a dedicated 14-axle line modular flat top trailer. Both shunt reactors were offloaded at the port onto stools for temporary storage. The Collett Team also transported and stored multiple ancillary components at our port side depot in Grangemouth. 

Utilising the 550Te capacity girder bridge with 20-axle lines, Collett transported the shunt reactors from Leith Docks to Innerwick. Due to narrow access along the remainder of the route, each of the two shunt reactors were transhipped from our 20-axle girder bridge on to a 14-axle flat top modular trailer in a dedicated road closure area, complete with all traffic management, in order to complete delivery. All movements were facilitated under police escort, as well as our in-house fleet of pilot vehicles.

Delivering Neart na Gaoithe

At the NnG onshire substation site, located in the Lammermuir HIlls, Collett’s Heavy Lift Team offloaded and positioned the shunt reactors into their final position using a hydraulic jacking and skidding system. Part two of the project is expected to take place in the coming weeks, when two 180Te supergrid transformers are due to be delivered to the wind farm site.

Share This Post: