Bolloré Logistics Tanzania delivers for the Songo Songo project

Rate this post

Bolloré Logistics Tanzania carried out the logistics for the Songo Songo project by transporting 5,000 freight tons of pieces and equipment. A total of seven barge vessels were required to deliver the equipment to the island at different intervals. Several specialised pieces of equipment were used including a 130-ton and a 60-ton crane, an excavator, a modular hydraulic trailer and 2 semitrailers for shunting. Other difficulties involved the lack of infrastructure. To this end, a jetty had to be rebuilt and converted into a landing area capable of accommodating the vessel and cargo arriving onto the island while backfilling works were undertaken to ease the flow of vehicles being used for shunting on and off the vessel. 

The main challenges were the coordination of the Customs requirements and the client’s demands, along with a lack of the equipment, including barges and ships. But with our expertise in logistics and industrial projects, we were able to deliver the required solutions with great success. All cargo was lashed and safely secured according to global QHSE standards,” said Elson Shan, Cluster Commercial Director

Bolloré Logistics Tanzania was contracted in 2021 to handle all logistical requirements for the project to set up a gas compression plant on Songo Songo island, located in the South of Tanzania. It was awarded to Bolloré Logistics’ teams by one of the largest suppliers in China of petroleum and petrochemical products, equipment, and technology to the global market. 

Share This Post: