Since 2018 the Port of Cannes has been carrying out renovation and reinforcement work on the Laubeuf and du Large seawalls. The main objective of this renovation work is to provide people and infrastructure with long-term protection against severe wave action, in harmony with the environment. The several involved contractors responsible for the lifting work on the construction site, consisting of a joint venture driven by TD Spada of Campenon Bernard / Group Vinci, Razel-Bec / Group Fayat and Negri, decided to use two Sennebogen telescopic crawler cranes: a 50 t crane and a 120 t crane will lift and move the loads along the promenade, both supplied by sales and service partner Sygmat.

The scheduling of this construction work has been divided into three separate phases, spread over three seven-month periods between October 2018 and April 2021, so that the pace of port activity and of major events hosted in Cannes is not interrupted. This will allow customers and professionals to continue using the port’s services without too many restrictions. Once finished, the seawalls will be redesigned to include a panoramic promenade, accessible to people with reduced mobility. This new 360° promenade, over 400 metres long, will connect that of the Quai Saint-Pierre to the facilities in the newly designed BoccaCabana district.

Storm surges are a recurring problem. Because during almost every one of them, the quay that reaches from the Old Port into the sea is under water. To remedy this situation, the quay is currently being reinforced with breakwaters over a length of 615 meters up to the helicopter landing platform. The construction of the wave return wall prevents the parking lot and the port facility from being flooded. The Sennebogen 653 E, rented and operated by Foselev, will be used to support the civil engineering work taking place there. Due to the limited space available on the lake promenade along the breakwater, the combination of compact size and lifting capacity of the 653 E telescopic crawler telecrane is the ideal choice. Thanks to its lifting capacities of up to max. 50 t, the Sennebogen 653 E covers a wide range of applications: lifting, moving and positioning large lifting loads, even on inclines of up to 4°. The powerful, up to 30.4 m long boom, which can be telescoped as a full-power boom even under load, allows flexible use on construction site.

The current protective armour (consisting of natural riprap) will be replaced by a protective armour composed of artificial concrete blocks, more precisely by 4 m3 accropodes made at Cannes la Bocca. The Sennebogen 6113E, rented out by ENCO, is handling and positioning the concrete blocks underwater. With a lifting capacity of 120 t, the Sennebogen 6113 E telescopic crawler crane is dedicated to support customers in the construction industry and crane rental.