Mammoet transports equipment for Sakhalin-2 project despite extreme conditions

Rate this post

Mammoet has transported 22 pieces of vital equipment to the onshore processing facility compression site (OPFC), as a part of the Sakhalin-2 project, located on the east coast of Sakhalin Island, Russia. The island is primarily home to abundant wildlife and therefore lacks enough infrastructure to complete projects of this scale. The biggest challenge was the lack of a sheltered port capable of withstanding the weight of the gas production equipment.

russia sakhalin lunskoye august 2019 23

The solution created for this challenge was a three-stage temporary beach landing. First, each of the 22 items were individually transferred from the transportation barge to an intermediate barge that was small enough to dock, then to the temporary beach landing facility and finally to the beach. The existing docking bay couldn’t withstand the 500t three phase inlet separator, so it was built a 200m temporary beach landing facility, which for environmental reasons was dismantled after the execution of works.

The temporary facility meant that Mammoet could transport the equipment off the barge using SPMTs. This transfer was challenging, especially for the items on the single trailers, because it was executed on open sea. Uncertain sea conditions directly affected the behaviour of the intermediate barge, and therefore Mammoet’s engineers needed to make precise calculations for every possible situation so that the transfer could take place. Once this step had been completed, the third and final stage was the 7km journey from the beach to the site.

russia sakhalin lunskoye august 2019 34

Mammoet’s Project Manager, Dmitry Matsiborko, explained: “The beach landing had several special requirements. It needed to be strong enough to carry the weight of the load, with an added focus on stability to counteract the extreme wind and sea conditions. The nearest settlement was over 100km away, so the smallest details required extensive preparation.”

Matsiborko concluded, “The initial schedule for the load-in to the island was 17 days, but Mammoet completed it in five. This successful execution helped us win additional scope for the installation of the three heaviest items at the OPFС site and transportation of the nine heaviest items to the installation area, so we are very happy with our efforts. We will now be able to adopt this same approach to projects with similar challenges in the future.”